This wall is a big deal and really unique. This wall is 538 ft. long; however, the last 250 ft. of the wall was built with a 5-degree incline as you ascend the ramp, parallel to the existing roadway. It was an unusual project because normally the top of the wall would be built horizontally. This project was engineered and designed by SFC Engineering and used the Redi-Rock Split Limestone texture. J&R Precast consulted and advised with SFC Engineering on the design of the unique five-degree incline. The entire site is managed by Market Basket Development and is completely visible from Rt. 128.